Invensys

Invensys Systems (UK) Ltd.


Triconex Home


Introduction to 
Turbo Machinery

Products

  TS110
  TS310
  310SV
  320
  TS3000
  TS3410
  TS3420

Auxiliaries

  HA100
  TurboSentry
  TurboMach.
  M306
  TS160

  Power Mgmt
  Compr. Ctrl

  Steam Tbn. 
  SOE
  TriLogger
  Gen. Ctrl.
  TMR-SOV

Guide to RfQ
Request Quote

Contact


TRICONEX
Invensys Systems 
(UK) Limited
Manor Royal
Crawley
West Sussex
RH10 9SJ

Tel: 01293 406 540
Fax: 01293 408 462

 

Power Management

Grid Controls

The screens for the grid controls show the status of the section and feeder breakers. The following is a summary of items shown on the screens.

Section Breaker status

Feeder Breaker status

Status of the CHP Mimic Panel

Status of the BMS Panel

Inputs  form the Hardwired I/O  11KV Breakers

Inputs for the Hardwired  Transducers as listed

Voltage and Frequency of each bus

MW, Amps and Power Factor  Alternators 1 & 2  

The following selections are available for operation of the electrical grid.

 

Open Breaker

Individual Open selections are provided for each feeder breaker.

Close Breaker

Individual Close selections are provided for each feeder breaker and bus coupler.

 

Loadshedding

Two graphics are provided for Load shedding. The screens display the load shed statuses for the individual devices and feeders. The following information is shown for each individual device or feeder breaker:

Activate            On the MMI this field is selectable. A device can be manually deactivated from the Load shed logic. This typically would only be done while performing maintenance.

Status  This field shows whether the breaker is open (green) or closed (red). If a breaker is open it is automatically taken out of load shedding.

Trip      This field shows if a breaker has been tripped (flashing red) due to load shedding. This field will turn off only after a RESET has been issued. This field is for indication only. The breaker can still be closed even if a RESET has not been issued.

Load    This field displays the load of each breaker in MW that is expected to be shed in the event of a load shed. The Feeder Breakers utilize a current sensor.

Priority This field shows the order in which breakers will be tripped during a load shed. The priority with the lowest number will be shed first.

Test     The field is selectable on the MMI. When this field is activated and the Master Test Switch is selected then the breaker will be shed.

There is special logic for load shedding   this will be  determined at  the functional design stage of the project .

In a split bus condition, a device normally powered by a feeder breaker on one side of the bus is assumed powered through the feeder breaker on the other side of the bus if the normal feeder breaker is open. For example if a feeder is normally powered on the right side of the bus is detected running and the right hand feeder breaker is open then it will be assumed the pump is powered from the left side of the bus.

The following selections are available for loadshedding.

Loadshed Enable

This enables or disables the entire load shedding system. The switch is automatically turned off if the load shed priorities are entered improperly, or there are generators connected to both the Main and Reserve buses or a Load shed Test is in progress.

Reset

Any breakers that are tripped by the load shedding system will remain flashing until this button is selected.

Loadshed Test

Activating a Test will immediately trip any breakers that are selected for testing. The Load shed Enable switch will be turned off.

Breaker Activate

This activates or deactivates individual devices or feeders from the load shed system.

Breaker Test

This activates or deactivates individual devices or feeders for the Load shed Test function.

 
Generator Controls

The screen for the generator controls will show the performance for  Alternators  9G-1,  8G-1,  8G-2 units.  Also  the system will be able to raise & lower the  setting of the AVR and  Governor control  from this system.   In addition the following will be  displayed.

 

Y.E. 11 KV Incomer No 1

KV,   KW,   FREQ,   P.F.,   Current.

Y.E. 11 KV Incomer No 2

KV,   KW,   FREQ,   P.F.,   Current.

Alternator 1

KV,   KW,   FREQ,   P.F.,   Current.

Alternator 2

KV,   KW,   FREQ,   P.F.,   Current.

Alternator 8G-4

MVAr & MW

 

 

Synchronization

Synchronizing the section buses can be accomplished from the Grid Overview 1 screen.

Left/Right Section Breaker

To synchronize and close the Left/Right Section breaker, select Close on the L1 breaker box on the screen. The frequency setpoint to the generators that are in Load sharing on the Right bus will be adjusted to bring the phase to 0 degrees. When the breaker is in phase, the breaker will be closed.  Ten synch check relay have been included to provide the final control permissive.

Bus Configurations  

 

 

 

 

 

 

Bus Configuration

The power capability of each of the running generators are added together to calculate the system capability.

The megawatt production of each of the running generators are added together to calculate the system load.

Split Bus Configuration

A split bus configuration is assumed if the Right / Left bus coupler (L1) is open.

The power capability of the generators are added together to calculate the left bus capability.

The megawatt production of the  generators are added together to calculate the left bus system load.

The power capability of the generators are added together to calculate the right bus capability.

The megawatt production of the generators are added together to calculate the right bus system load.

 

 

Instantaneous Load shedding

Instantaneous Load shedding Permissives

The following permissives are required for instantaneous load shedding:

Load shed Enabled

Either all or none of the online generators are connected to the Main Bus

Peer to Peer communication healthy to all UCP’s that are On-Line

Priority list is correctly entered.

Instantaneous Load shedding Logic

If a generator trips, the current megawatt production is compared to the total capacity of the running generators. If the megawatt production exceeds approximately 90% of the total capacity, the excess load will be shed.

The priority of each device is selectable. Each device priority must be unique and a number from 1 to 30 or load shedding will be disabled. Since this logic concerns load shedding, the number 1 is the lowest priority and 30 the highest priority. Therefore Priority 1 is tripped first in a load shed and Priority 30 is tripped last.

The Megawatt load of each feeder breaker is estimated from an AC current transducer, power factor is estimated. Loads that are not measured are manually input based on the normal operating duty in MW. If the actual current for the individual loads is not available then the load will be estimated. Only the necessary amount of load will be shed.


 
Time based (Frequency) loadsharing  

 

 

 

 

 

 

 

 

 

Time Based Loadshedding Permissives

The following permissives are required for time based load shedding:

 

Loadshed Enabled

Frequency is decreasing

The Time Delay (300 ms) after a Previous Time Based Load shed has expired

Either all or none of the online generators are connected to the Main Bus

Either all or none of the online generators are connected to the Reserve Bus

Priority list is correctly entered.

Time Based Load shedding Logic

Time Based or Frequency Load shedding occurs if the permissives listed above are satisfied and the criteria below is met:

If the frequency is less than  49.5 hz (96%) then 10% of the load will be shed.

Progressive Loadshedding

Progressive Loadshedding Permissives

The following permissives are required for Progressive load shedding:

Load shed Enabled

Either all or none of the online generators are connected to the Main Bus

Priority list is correctly entered.

Progressive Load Shedding Logic

Progressive Load shedding occurs if the permissives listed above are satisfied and the criteria below is met:

If the Megawatt Load increases above 95% of the available capacity then an estimated load will be instantaneously shed to bring the Megawatt Load below 90% capacity.


 

Auto Synchronizing - Bus Couplers

A common set of synchronizing hardware is used for both of the bus coupler breakers. The hardware required for synchronizing consists of a phase transducer, sync check relay, and a Multilin relay consisting of three-phase voltage and frequency.

The Right Bus is always connected to one side of the phase transducers and sync check relay. The other side of the phase transducer and sync check relay is either connected to the Left Bus or the Reserve Bus. This is determined by a bus selector relay.

If the Reserve Bus Coupler is detected closed and the Main / Left Bus Coupler is open then the bus selector relay is set to the Left Bus. If both Bus Couplers are open then the bus selector relay remains in the last position. If a breaker close command is selected and the bus selector relay is in the wrong position then it will change to the correct position.

If the Right / Left bus coupler (L1) is open then the frequency setpoint to the right bus generators will be adjusted to maintain a 0 degree phase angle. The breaker will be closed if the following are met::

Bus Selector is in the correct position

Sync Check Relay is Energized

If either bus is dead there must be no generator breakers closed to the bus

If both buses are live then the phase angle must be within 5 degrees

If both buses are live then the frequency must be matched within .05 hz.
           

If the Right / Reserve bus coupler (R1) is open the breaker can be closed if the following are met:

Bus Selector is in the correct position

Sync Check Relay is Energized

If either bus is dead there must be no generator breakers closed to the bus

If both buses are live then the phase angle must be within 5 degrees

If both buses are live then the frequency must be matched within .05 hz.

If both buses are live it indicates that generators are connected to both the right and reserve bus. Load sharing is not permitted in this instance. Therefore the frequency of the right bus must be manually increased to facilitate the phase angle and frequency requirements.
 


Auto synchronizing - Generators

For the most part the  Governor control system  for each generator performs the Auto Sync functions.

 

 

 

 

 

 

 

 

 

 

 

^

© Copyright 2002-2007 Invensys Systems (UK) Ltd. All rights reserved.
Legal Information.